Whether a no-damages-for-delay clause will be enforced against you, and the deadline for bringing a construction contract claim.
“No damages for delay” clause enforceability
Public contracts: Ariz. Rev. Stat. Section34-221(F) requires public construction contracts to include a provision for negotiating delay damages caused by the agency, for unreasonable and uncontemplated delay -- functionally voiding a pure no-damages-for-delay clause. Private contracts: unresolved by Arizona courts, though an unreported 2018 decision acknowledged the majority 'active interference' exception.
For public contracts, Ariz. Rev. Stat. Section34-221(F) requires a provision allowing the contractor to negotiate recovery of delay damages for agency-caused delay that is unreasonable and outside the parties' contemplation; Tech. Constr., Inc. v. City of Kingman, 278 P.3d 906 (Ariz. Ct. App. 2012) confirmed a city could not escape this via a 'no liability' clause. For private contracts, Arizona courts have not conclusively addressed enforceability; an unreported, non-precedential 2018 Court of Appeals decision (Sw. Concrete Paving Co. v. SBBI, Inc.) acknowledged that no-damages-for-delay clauses are generally enforceable but that many states recognize an 'active interference' exception -- though the court did not resolve whether Arizona adopts it, since the contractor had waived the argument.
Citation: Ariz. Rev. Stat. Section34-221(F); Tech. Constr., Inc. v. City of Kingman, 278 P.3d 906 (Ariz. Ct. App. 2012) (public); Sw. Concrete Paving Co. v. SBBI, Inc., No. 1 CA-CV 17-0294, 2018 WL 2307002 (Ariz. Ct. App. May 22, 2018) (private, non-precedential).
Source: https://50-state.watttieder.com/states/arizona/
RESEARCHED via a detailed 50-state survey (Watt Tieder LLP). Prior entry said 'None found' -- Arizona actually has real, on-point public-contract authority and a persuasive (though non-precedential) private-contract case.
Construction contract filing deadline
6 years for a written contract executed in Arizona
Arizona's limitations period for a debt action founded on a contract in writing executed in the state is 6 years from accrual, covering an ordinary written construction-contract claim.
Citation: A.R.S. § 12-548
Source: https://codes.findlaw.com/az/title-12-courts-and-civil-proceedings/az-rev-st-sect-12-548/
A separate 8-year statute of repose applies to construction-related claims (A.R.S. § 12-552) rather than an ordinary payment dispute; that repose period wasn't independently verified against a primary source this pass.