Construction Delay Claim: Supporting Documents Checklist

A delay and extended overhead claim stands or falls on whether you can show the delay happened, that it was on the critical path and what it cost. These are the records an owner, surety or carrier will expect to see alongside the calculation.

14 items across 4 categories. This is a general guide for a typical claim of this type, not an exhaustive or jurisdiction-specific list. Confirm exact evidentiary requirements with counsel before submission.

Advertisement

Why the record matters

An Eichleay or extended-general-conditions claim is a damages calculation resting on an evidentiary record. The formula is only as defensible as the daily logs and schedule updates behind it, which is why reviewers ask for the backup before they engage with the arithmetic.

The checklist

Contract & Baseline

  • Executed prime contract / subcontract
  • Approved baseline schedule
  • Approved schedule of values / budget

Time & Delay Evidence

  • Daily/weekly job logs covering the delay period
  • Superintendent or project manager diaries
  • Delay notices and written correspondence
  • Updated/as-built schedules showing critical-path impact

Cost Backup

  • Change orders (approved and pending)
  • Payment applications / invoices
  • Payroll or certified payroll records
  • Vendor and subcontractor invoices

Photos & Site Records

  • Dated site photographs
  • RFIs and responses
  • Meeting minutes referencing the issue

What each document proves

A checklist is only useful if you know why each item is on it. Reviewers do not ask for records to be thorough; they ask because each one answers a specific question that the calculation on its own cannot.

Contract & Baseline

Executed prime contract / subcontract

What it proves. Establishes the time obligation you are claiming was disrupted, the notice provisions you had to satisfy and whether a no-damages-for-delay clause applies at all.

Where it comes from. Your own contract file. Get the fully executed version with all exhibits, not the draft that circulated before signature.

Approved baseline schedule

What it proves. The measuring stick. Without an accepted baseline there is no agreed starting point from which to show slippage and a reviewer can characterise any delay as your own planning error.

Where it comes from. The schedule submittal that the owner or architect accepted, with the transmittal or approval letter attached.

Approved schedule of values / budget

What it proves. Ties the contract price to work packages, which is what makes an allocation of overhead to this contract reviewable rather than asserted.

Where it comes from. The SOV attached to your first payment application, plus any approved revisions.

Time & Delay Evidence

Daily/weekly job logs covering the delay period

What it proves. The single most-requested record in a delay claim. Contemporaneous logs show crew counts, weather, deliveries and idle time on the specific days you say work stopped.

Where it comes from. Site supervision. Pull the full run covering the delay window plus two weeks either side, not just the days you intend to claim.

Superintendent or project manager diaries

What it proves. Corroborates the logs from a second, independent hand and often captures the reason for a stoppage that the formal log records only as an absence of progress.

Where it comes from. Individual staff. These are frequently personal notebooks rather than company records, so ask early, before someone leaves.

Delay notices and written correspondence

What it proves. Proves you gave the notice the contract required, when it required it. A meritorious delay claim is regularly defeated on notice alone.

Where it comes from. Project correspondence file, transmittal log and the project email archive. Check sent items, not just what was filed.

Updated/as-built schedules showing critical-path impact

What it proves. Distinguishes a delay that pushed completion from one absorbed by float. Only critical-path delay supports extended overhead.

Where it comes from. Monthly schedule updates as submitted, plus a final as-built. If updates were never issued, a retrospective as-built analysis will need to be built and that costs more.

Cost Backup

Change orders (approved and pending)

What it proves. Shows what time and money has already been granted, which prevents you claiming the same day twice and shows the reviewer you have netted out what was settled.

Where it comes from. Change order log. Include pending and rejected ones; the rejections often carry the owner's own characterisation of the delay.

Payment applications / invoices

What it proves. Establishes contract billings for the performance period, which is the numerator in the Eichleay allocation.

Where it comes from. Accounting. You need the billings for this contract and the company-wide total for the same period, from the same system and the same basis.

Payroll or certified payroll records

What it proves. Supports the labour hours behind an inefficiency claim and demonstrates that crews were actually on site during the extended period.

Where it comes from. Payroll system, or the certified payroll submissions if this is public work.

Vendor and subcontractor invoices

What it proves. Backs the daily general conditions rate with real costs rather than an allowance: trailer rental, temporary utilities, fencing, portable toilets, security.

Where it comes from. Accounts payable, filtered by job number for the extended period.

Photos & Site Records

Dated site photographs

What it proves. Converts a written assertion into something a reviewer can see. Photographs of an idle site on specific dates are difficult to argue with.

Where it comes from. Site staff phones, drone surveys and any progress-photo service. Confirm the EXIF dates survived whatever the photos were copied through.

RFIs and responses

What it proves. Documents when you asked and how long the answer took, which is often the cleanest available evidence of owner-caused delay.

Where it comes from. The RFI log, with dates submitted and dates answered both intact.

Meeting minutes referencing the issue

What it proves. Shows the delay was raised contemporaneously and, frequently, that the other side acknowledged it before positions hardened.

Where it comes from. Progress meeting minutes. The owner's or architect's own minutes carry more weight than yours.

Gaps that weaken this claim

These are the omissions that cost real money, in rough order of how often they come up.

No contemporaneous schedule updates.

If monthly updates were never issued, critical-path impact has to be reconstructed after the fact. That is expensive, contestable and the single most common reason a delay claim gets discounted.

Notice given late, or given verbally.

Most contracts require written notice within a fixed number of days. A claim with merit and no timely written notice is regularly defeated on the notice provision alone.

Delay days counted differently in different places.

The compensable day count used for extended field overhead must match the one used for the Eichleay allocation. Reviewers check that they reconcile and a mismatch undermines both.

Home office and field overhead blended together.

They are separate costs proved by separate records. Combining them into one daily rate makes the whole figure look assembled rather than calculated.

Frequently asked questions

How far back should the daily logs go?

Pull the full run for the delay window plus roughly two weeks either side. The days before the delay establish the normal rate of progress you are comparing against and reviewers frequently ask for them.

What if we never issued formal schedule updates?

A retrospective as-built schedule can be built from daily logs, payment applications and photographs, but it costs more and carries less weight than contemporaneous updates. Start gathering the underlying records now rather than later.

Do we need all of this before running the calculator?

No. The calculator is free and unlimited and running it first tells you roughly what the claim is worth, which is how you decide whether the document-gathering effort is justified.

Tick these off as you go

The ClaimDuke calculator carries this same checklist. Tick what you already have and add your own items and they carry through to the Excel workbook, the Word document and the PDF report you export, so what you hand over shows exactly which records are in the file and which are still outstanding.

Build the calculation and the checklist together

Free to calculate, with a free one-page summary. Paid reports add your branding, a live-formula Excel workbook and the cited methodology behind every line.

Check your state's rules

Evidentiary expectations and the underlying entitlement both vary by jurisdiction. ClaimDuke carries a cited reference for all 50 states + DC covering statutory interest, actual cash value and labor depreciation, delay-claim limits and injury liability.