Change orders (approved and pending)
What it proves. Shows what time and money has already been granted, which prevents you claiming the same day twice and shows the reviewer you have netted out what was settled.
Where it comes from. Change order log. Include pending and rejected ones; the rejections often carry the owner's own characterisation of the delay.
Payment applications / invoices
What it proves. Establishes contract billings for the performance period, which is the numerator in the Eichleay allocation.
Where it comes from. Accounting. You need the billings for this contract and the company-wide total for the same period, from the same system and the same basis.
Payroll or certified payroll records
What it proves. Supports the labour hours behind an inefficiency claim and demonstrates that crews were actually on site during the extended period.
Where it comes from. Payroll system, or the certified payroll submissions if this is public work.
Vendor and subcontractor invoices
What it proves. Backs the daily general conditions rate with real costs rather than an allowance: trailer rental, temporary utilities, fencing, portable toilets, security.
Where it comes from. Accounts payable, filtered by job number for the extended period.