Free sample report

Sample Construction Delay & Extended Overhead Report

This sample shows how ClaimDuke presents a delay and extended overhead claim: the Eichleay allocation for unabsorbed home office overhead, daily extended field overhead for the compensable delay period, and an MCAA loss-of-efficiency factor applied to affected labor.

The sample is a five-page watermarked PDF using illustrative figures, not real project data. Your own report is generated live from the numbers you enter and is not watermarked.

Advertisement

What the sample contains

Methodology used in this report

Eichleay Formula

Allocable Overhead = (Contract Billings ÷ Total Firm Billings) × Total Firm Overhead. Daily Rate = Allocable Overhead ÷ Actual Days of Performance. Damages = Daily Rate × Compensable Delay Days.

Extended Field Overhead

Daily Field Overhead Rate × Compensable Delay Days, covering trailer, supervision, utilities, rentals and insurance held on site through the delay.

MCAA Loss-of-Efficiency

Affected Labor Cost × MCAA Factor, drawn from the MCAA 'Factors for Weighted Average Loss of Productivity.'

What the paid Excel workbook looks like

The sample PDF above shows the report. This is the Full Line-Item Breakdown sheet from the formatted Excel workbook a paid report also includes, rendered from an actual generated workbook rather than a mock-up. Every figure on it is a live formula reading from an Inputs tab, so changing an input recalculates the whole workbook.

Full Line-Item Breakdown sheet from the ClaimDuke Construction Delay & Extended Overhead Excel workbook, showing each intermediate calculation step with a summary and total.
Excel workbook, Full Line-Item Breakdown sheet. Lower rows are obscured on purpose; the full sheet comes with a paid report.

Sample versus a paid report

The sample is a fixed, watermarked PDF. A paid report is generated live from your own figures and adds a formatted Excel workbook with working formulas, a matching Word document, an unwatermarked PDF and your own logo or letterhead. The monthly plan additionally includes a Scenario Comparison sheet for modelling conservative, likely and aggressive positions.